Misericordia Health Center Operating Room Upgrades

Project Start: Spring 2026

The work on this project includes upgrades to the mechanical systems of the fourth floor operating rooms at the Misericordia Hospital. This is a four phase project, consisting of the abatement of existing asbestos containing GWB ceilings for access. The existing fan coil units will be removed and replaced along with the chilled water piping, adding in new shut off and balancing valves on the chilled water mains. New controls will be installed for the fan coils and the system tested and commissioned. The GWB ceilings will be repaired and painted following the completion of the mechanical upgrades. The project is expected to take approximately 16 weeks and will start in April 2026 pending permits and confirmed material deliveries